Installing h-frames, relocating att equipment, temp relocation of tmo equipment from the existing h frame. Need to see photos but most likely install new hframe with new PPC, if conduits are too small (most likely) run new conduits with cabling to the cabinet location. Prep the new cabinet. At the same time up on top, mount mod for the top sector, hot slide existing antennas install new ones, install hybrids prepare for cutover, cutover: install new cabinet, connect new power wire,hybrids, gps, etc. put the site on air (to minimize site outage)
Install the 2nd cabinet ( might be already installed) connect everything on the ground + grounding of the new cabinets, finish up on top, decom legacy equipment from both CLs, decom mounts, old hybrids, etc. Dress up, clean up, wrap up.
Это как бы делал я, давно нокию не строил, по этому могу где-то ошибиться. А вообще я бы привез генератор, передвинул существующий кабинет, переподключил бы его на темп Пауэр, и спокойно закончил весь низ без всяких отключений, за это время на верху все было бы готово к катовер...как-то так